Referances

Capacity Of the Plant1
Capacity Of the Plant2
Our Scope 


Manufacturing of Watermeter1
Manufacturing of Watermeter2
Electrical&Instrumentation jobs 
 

 

Beginning date Plant 1 
Beginning date Plant 2

24.4.2004
10.6.2009
 

 

Finishing date Plant 1
Finishing date Plant 2

 

15.10.2004
15.1.2010

 

 

Technical Person 

2 Engineer
2 Forman
6 Electrical skilled
1 Mechanical skilled
1 Welder
15 Helper
 

 

Some quantities on our Scope



TR Installation(1x1600+1x2500)
Generator Installation   
ADP Installation
MCC Installation 
DistributionPanels
Cable tray Installation(100-600mm)
Conduit Installation(1/2 "- 6 ") 
Instrument Installation
Power cable Installation
Signal Cable Installation
F/O Cable Installation
MV Cable Installation
Lighting Cable installation
Lighting Poles & Fixtures
 

 

4.100 Kva
750 Kva
1 Nos
2 Nos
12 Nos
600 mt
240 mt
17 Nos
3450 mt
2100 mt
170 mt
360 mt
1600 mt
280 Nos